ENERGY EFFICIENCY SUBSCRIPTION FOR DEEP RENOVATION WITH PERFORMANCE GUARANTEE

Deliverables

Communication&Dissemination Plan

A first version of the plan will be delivered in month 3 by ESEB and it will be updated in month 18

Project Leaflet

Two project leaflets one customized for end users and one for market operators will be prepared to address the right starting messages to the different target groups They will be printed in a sufficient numnber of copies in order to reach the audience but taking into account the will to avoid useless paper use

5 regional videos on results

5 regional videos on main achievements will be produced for each involved region

Project branding package

The visual project identity will include a logo hashtag a motto and a graphical identity

Project brochure and video

1 digital version brochure with different sections tailored for specific target groups so that each user can access the information mostly fitting to its own profile An explanatory video of the project concept is also going to be produced

4 feasibility studies for replication

The studies offered to those who signed D46 will be developed by F3 in order to define the conditions under which the replication of the project in different areas could be effective

5 Business plans

Five business plans are developed to explore future exploitation of the project on a long term perspective

Report of meetings with market op.

The report is based on the outcomes of the workshop organized in T21

Set of criteria

A set of criteria to select folloers institutiins will be defined jointly by the consortium

Business plan for long term replication

The plan defines the conditions under which project activities can be replicated further with a a self sustained financing mechanism based on knowledge transfer

Evaluation of learning programs

The training activities will be assessed in order to assess the transferability impact

Training package

The training package will be used with potential replicators

Final project publication

The final pubblication will summarize all main lessons learnt results and impact achieved It will be the final project publication

Call for selection

On the basis of the criteria set in T41 the call for the selection of potential replicators

Dissemination activities Reports

The report will summarize all the dissemination activities implemented It will be drafted in month 18 and updatedin the final version in month 36

Report of meetings with financial inst.

The report is based on the outcomes of the workshop organized in T22

Report on replication activities

The report provides the outcomes of the replication activities implemented by the consortium

Subscribers list + updates

A first list of market operators adopting the EES will be developed at month 24 and updated at month 34

Communication&Dissemination Report

The report will be structured as the Communication and Dissemination Plan and will be used to report the activities implemented

Endorsement acts

The endorsement could be an official act or statements as outcomes of meetings or exchange of official letters This will depend on the different practices in place in the different institutions approached

Project events Reports

The report summarize all the evnts where the project was present A first release of the report is expected at month 27

4 agreements with replication partners

Four agreements with the four most promising trained partnes will be signed with F3 in order to ensure the development of D47

5 EESs adapted

Based on the outcomes of 23 and outcomes of 21 and 22 the deliverables include all the technical specifications and documents tailored at regional level thta will be promoted with the WP3 activities

Energy Efficiency Subscription scheme

The deliverables includes all the specifications and standard contract schemes to be discussed with stakeholders at regional level

Data Management Plan

The plan developed at month 6 will be updated at least once at month 12

Web platform + user manual

The web platform includes all specifications and documents of D2.4 and make it usuable for end users and market operators.