Skip to main content
European Commission logo
italiano italiano
CORDIS - Risultati della ricerca dell’UE
CORDIS
CORDIS Web 30th anniversary CORDIS Web 30th anniversary

Unified DR interoperability framework enabling market participation of active energy consumers

Risultati finali

Plan for the deployment of the DRIMPAC solution and required equipment to pilot premises

A deployment plan based on: a) the building requirements, b) the DEDMF requirements, c) the deployment strategy, and d) the required procurement and installation activities. Associated Task: T4.4

DRIMPAC replication roadmap

Analysis of the replication feasibility for the new business models for utilities assessment of their viability and definition of best practices to be communicated towards relevant target groups Associated Task T54

Pilot activity preparation checklist

This report will include include requirements (e.g. permissions, RFP regulations) and estimated timelines for the prerequisites satisfaction so as to facilitate timely preparation of the pilot sites that may operate under different regulatory, legal, cultural and market frameworks. Associated Task: T4.1

Report on activities for the definition and promotion of DRIMPAC standardization punch-list v.1

This document will define the standardization punch-lists, the concrete proposal for standards extensions that would be required in order to enable the benefits of the DRIMPAC system and overall approach. A preliminary version will be prepared on M18. Associated Task: T5.1

Demand Response stakeholder requirements for the DRIMPAC solution

This report will capture the business cases and requirements of all DR stakeholders holistically so as to accurately set the context for the creation of the DRIMPAC solution. Associated Task: T1.3

Consolidated report on the innovative business models for energy retailers

Market analysis and further elaboration and validation of the new business models for utilities Associated Task T54

DRIMPAC cost-benefit analysis and impact assessment

A report on a holistic costbenefit analysis and impact assessment of the replication and wide adoption of the DRIMPAC solution in the EU Associated Task T52

Policy/market reform recommendations report v.2

Recommendations regarding policyregulation as well as market structures in order to create a friendlier environment for the adoption of DRIMPAC results to enhance active participation of energy consumers in markets and the proliferation of interoperable building automation technologies Final version Associated Task T53

Report on establishment and recruitment activities for the User Group and Stakeholder Ecosystem

This document will report the actions taken by the consortium and their results on the establishing the “User Group” and “Stakeholder Ecosystem” communities. Associated Task: T1.1

Policy/market reform recommendations report v.1

Recommendations regarding policy/regulation as well as market structures in order to create a friendlier environment for the adoption of DRIMPAC results to enhance active participation of energy consumers in markets and the proliferation of interoperable building automation technologies. First version. Associated Task: T5.3

DRIMPAC technical specifications and system architecture

This deliverable will contain the concrete technical specifications for the DRIMPAC IT system and its detailed system and software architecture. Plans for integration, testing and pre-validation deployment will be specified. Associated Task: T1.4

Performance Measurement & Verification methodology report

This deliverable will include a comprehensive Performance Measurement Verification methodology that will guide all pilot demonstration and validation activities of WP4 Associated Task T15

Analysis of standards and protocols in the building automation and demand response domains

This document will provide an analysis on existing standards and protocols with the aim to identify their suitability or potential limitations to support the deployment and operation DRIMPAC business models Associated Task T21

Report on activities for the definition and promotion of DRIMPAC standardization punch-list v.2

This document will define the standardization punchlists the concrete proposal for standards extensions that would be required in order to enable the benefits of the DRIMPAC system and overall approach This is the final version Associated Task T51

Ex-ante analysis and baseline estimation for pilot premises

A report on the preevaluation deployment and data gathering activities aiming to establish the proper onsite operation of the system and estimate the baseline at the pilot sites Associated Task T46

Report on dissemination & communication activities

A document that will report the dissemination and communication activities towards informing the society and public at large about the outcomes of the project Associated Task T61

Innovative energy retailer business model proposal and market analysis

This deliverable will comprise an investigation of the existing offerings and business models of energy retailers and competitive entities, such as aggregators, and propose innovative business models including feedback from the Stakeholder Ecosystem. Associated Task: T1.2

DRIMPAC solution holistic evaluation

A consolidated evaluation for providing individual aggregated and comparative assessments of pilot results considering a the technical performance of the DRIMPAC solution b its effectiveness in reducing building energy costs facilitating selfconsumption and increased participation of consumers in the market c its efficiency in discovering and delivering the expected demand flexibility d the interactions between the system and human users e the overall satisfaction and acceptance of the pilot users Associated Task T46

Report on activities for engaging and training pilot participants and related material

This document will report the actions undertaken for the recruitment and preparation of the citizens who will participate in the pilot validation activities. Associated Task T4.2

Report on the operation and use of the DRIMPAC solution during pilot testing

This document will report the results of the DRIMPAC solution operation at the pilot sites entailing the evaluation of its impact and performance under reallife conditions Associated Task T45

DRIMPAC dissemination and communication plan and associated material v.3

This report is the second update of the Dissemination and Communication Plan DCP describing the projects strategy activities and implementation instruments including training activities Associated Task T61

DRIMPAC branding, website and social media channels

Project branding as the forerunner to ensure a distinctive, attractive identity in all communication tools to be produced including: project logo, website graphic design templates, banners, leaflets, etc. Project website and social media channels establishment. Associated Task: T6.1

DRIMPAC dissemination and communication plan and associated material v.2

This report is the first update of the Dissemination and Communication Plan (DCP) describing the project’s strategy, activities and implementation instruments including training activities. Associated Task: T6.1

DRIMPAC dissemination and communication plan and associated material v.1

D6.2 DRIMPAC dissemination and communication plan and associated material

DRIMPAC Common Information Model and Ontology

This deliverable will report the ontology based common information model developed in the project and its mapping to DR relevant standards like OpenADR and OneM2M Associated Task T22

Pubblicazioni

One Step Ahead Energy Load Forecasting: A Multi-model approach utilizing Machine and Deep Learning

Autori: A. Mystakidis et al.
Pubblicato in: 7th International Universities Power Engineering Conference (UPEC), 2022, 2022
Editore: IEEE
DOI: 10.1109/upec55022.2022.9917790

OPENADR-based information and communication infrastructure for implicit demand response scenarios

Autori: G. Damousis ; E. Bazouki ; D. Agtzidis ; D. Tzovaras ; P. Barrachina ; R. Perez de Zabalza ”, T,
Pubblicato in: The 12th Mediterranean Conference on Power Generation, Transmission, Distribution and Energy Conversion (MEDPOWER 2020), 2021, Pagina/e p. 276 – 282
Editore: IET digital Library
DOI: 10.1049/icp.2021.1206

A Business Model Fast Track on Energy Communities—Key Lessons Learned from H2020 EU Projects

Autori: Breukers, S.; Schibline, A.; Pressmair, G.; Barnes, J.; Perrio, M.F.; Calatayud, E.P.; Rakocevic, L. A
Pubblicato in: Key Lessons Learned from H2020 EU Projects, Numero Environ. Sci. Proc. 2021, 11, 19, 2021
Editore: MDPI
DOI: 10.3390/environsciproc2021011019

A design framework for Citizen Energy Communities in Cities: exploring PV-storage synergies

Autori: I. Poursanidis, G. Rancilio, E. Kotsakis, G. Fulli, M. Masera, M. Merlo
Pubblicato in: 11th IEEE PES Asia-Pacific Power and Energy Engineering proceedings, 2019
Editore: IEEE

DRIMPAC—Unified Demand ResponseInteroperability Framework Enabling MarketParticipation of Active Energy Consumers

Autori: Dimitrios Tzovaras, Ioannis Damousis, Antonis Papanikolaou, Giorgos Pitsiladis, Giulia Barbagelata
Pubblicato in: Sustainable Places 2019, Numero Proceedings 2019, 20, 15, 2019
Editore: MDPI

Addressing Demand Response Interoperability Challenges for Small Prosumers — The DRIMPAC Project Concept

Autori: D. Tzovaras, A. Papanikolaou, G. Pitsiladis, I. G. Damousis, G. Georghiou
Pubblicato in: 2019 1st International Conference on Energy Transition in the Mediterranean Area (SyNERGY MED), 2019, Pagina/e 1-6, ISBN 978-1-7281-3087-3
Editore: IEEE
DOI: 10.1109/synergy-med.2019.8764141

Integration of Renewables in DHC for Sustainable Living Workshop

Autori: María Victoria Cambronero Vázquez; Jack Corscadden; Antonio Garrido Marijuan; Giulia Barbagelata; Georg Hamann; Matthieu Grosjean; Nora Mendoza
Pubblicato in: instname:Fundación Tecnalia Research & Innovation, Numero 1, 2020
Editore: MDPI
DOI: 10.3390/proceedings2020065030

È in corso la ricerca di dati su OpenAIRE...

Si è verificato un errore durante la ricerca dei dati su OpenAIRE

Nessun risultato disponibile