Periodic Reporting for period 2 - COMPOSKE (Development of a new technology for production of Skeletons in composite materials for realization of pre-cast tunnel segments.)
Reporting period: 2016-07-01 to 2017-06-30
The main phases of this project are:
• Definition of skeleton typologies,
• Production of prototypes of segments with GFRP reinforcement for final testing program,
• Validation of the numerical models and the final definition of a proper reinforcement for the segment,
• Development of Manufacturing Technologies and production of final demonstrator for industrialization,
• Experimental test on final demonstrators, validation of entire project, qualification of products and of process,
• Exploitation and dissemination of project results.
The typologies individuated are: ring, lattice and wirenet reinforcement.
The drawings for prototype phase was carried out taking into account two different tunnel Typologies: typical metro tunnel and typical hydraulic tunnel.
A new Manifacturing Technologies has been designed and built to produce reinforcement. The reinforcement have been assembled so as to make the different prototypes . Experimental test related to prototypes are in progress at Laboratory of Tor Vergata (University of Rome).
The data processing obtained from the tests will allow the choice of the final prototype.
A plan of dissemination and exploitation of project results was drawn up.
By using ATP new reinforcement there are many economic benefits : a reduction of thickness concrete of the tunnel segment because these products doesn’t corrode and so there isn’t need of big concrete cover to protect it unlike steel; and in the case of temporary application the segment reinforced by GFRP will be easier and more economical to be demolished and also safer for workers and jobsite.